Evangelical Community Hospital

Client Profile

Since 1926, Evangelical Community Hospital has promised and delivered the very best to its patients and their community by providing compassionate and accessible health care.

Client Challenge

In 1999 they had a growing need for physical therapy work hardening, but did not have the space for this service.

The Mobilease Solution

Evangelical Community Hospital contacted Mobilease and we designed, built, and installed a 5,000 sq. ft. modular physical therapy building with offices, exam rooms, showers, and large therapy areas with one section having an impressive 11’ interior ceiling. This physical therapy building now helps patients become reacclimated with their jobs.

Project Schedule

Contract Awarded

10.1.99

Drawing Review / Approval

10.29.99

Permit Issued

11.5.99

Site Preparation

11.10.99

Delivery & Installation

11.11.99

Project Completed

12.31.99
“We are very happy with the way the modular turned out, we knew the value of the speed and cost, but were not sure of the quality of the finished product. We now are equally as happy about the construction quality of the structure itself."

Terry Napp

EVANGELICAL HOSPITAL
If you need additional space, temporarily or permanently, our experienced staff can help you through the process, from design and planning to site work and installation.

We provide turnkey services to make your project go smoothly.

Contact Us